Lancaster Patient Care Center Construction Update September 12, 2019

Lancaster Patient Care Center Construction Update September 12, 2019

The majority of the site grading has been completed at the new Lancaster Patient Care Center. The new staff parking lot paving will be completed next week.  Granite curbing has been installed along the new Ground level entrance sidewalk.  Now the concrete forms can be placed and poured.  Landscaping is well underway with a final design being submitted next week.

The 2nd level window opening used to pass building materials to this area will be installed next week. The masons have been laying brick exterior in the patio area this week to allow the final landscaping to be completed. The exterior masonry is behind schedule, but this will not impact the overall schedule.

The mechanical and electrical rooms are actively being worked on. The electrical panels are installed and the boiler installation is in progress. Plumbing fixtures are being hung in bathrooms and exam rooms.

There has been good progress in the Oncology and Wound Care centers the past couple of weeks. The sprinklers are in place.  The painting of walls is substantially complete. The installation of the millwork is in process. The electrician has started the finish electrical work. A good portion of the flooring is in place.

On the 1st floor the sprinklers are in place. The painting of the walls is substantially complete. The installation of the millwork is in process. The finish electrical work is in process and most of the flooring has been installed.

The 2nd floor drywall is complete. A good portion of the walls are painted.  Flooring has been installed in several of the offices and exam rooms. Rough mechanical and electrical are in place. More work is needed to complete the sprinkler installation.

The elevator assembly will take another week before the final check out phase is completed.  The State of New Hampshire will need to inspect all aspects of the elevator installation and operation before an operating certificate can be issued.

Overall, work is moving along nicely. Look for our grand opening this December. And don’t forget to make a donation to the building campaign.